SPECIAL CASE NAME
High Volt transformer rigging of TPC next to Taipei-101
ENGINEERING TIME
2017.01.05~2017.01.22
ENGINEERING OUTLINE
Use Pull-up system to rise transformer up and then skidding 100m in the basement 4 floor. Lift it up to ground by strand jack combine onto hydraulic gantry L802 and rotate 90 degree for skidding out again. Loading transformer onto trailer after skid-in lifting area, and then truck back factory for maintenance.